Posts Tagged ‘Phoenix NAP’

New Phoenix NAP blog!

We have recently launched a new Phoenix NAP blog at blog.phoenixnap.com. Give it a look to catch the latest news about the full service data center, or to get some more information on industry-related topics.

The Datacenter Builder blog will remain in place, to focus more on any construction-related activities or expansions.

Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



Phoenix NAP Installs New Generators

August 12, 2011- Update! New generators were installed at Phoenix NAP data center in late June. These were put in place to assist in the expansion of Phoenix NAP’s second floor. Here are some great photographs!

Generators Photo 1   Generators Photo 2   Generators Photo 3
Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



Updating the Online Property

Website Screenshot

April 22, 2010 – Up until now, most of the posts within this blog have centered around construction activity and related images and video footage. With our grand opening approaching, this will continue for a little while yet, but today we shift focus to another sort of property – a Web property.

Earlier this week, our company Web site received a face lift of sorts. A new design was implemented reflective of a premier datacenter, and additional content was added regarding our facility’s security attributes, the services we offer, industry articles that have featured us, video interviews, and information about our preferred partners.

If you have not yet seen the new site, check out PhoenixNAP.com today. In the meantime, here are a few screen captures of it.


Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



Generator Installation

February 5, 2010 – The equipment is beginning to be installed in our backyard! As evidenced by these photos, the Cummins generators are going in. The back-up generators are arranged in an N+1 configuration, for added redundancy.

Generator Photo 1   Generator Photo 2   Generator Photo 3
Generator Photo 4   Generator Photo 5   Generator Photo 6
Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



January 6, 2010 – Second Floor and Yard Construction

The calendar states 2010 and our upcoming grand opening is quickly approaching.

The second floor of our datacenter continues to be installed and the equipment yard is being prepped and reconfigured for the installation of generators, UPS units, and modular central plants.

Second Floor and Yard Photo 1   Secong Floor and Yard Photo 2   Second Floor and Yard Photo 3
Secong Floor and Yard Photo 4   Secong Floor and Yard Photo 5   Secong Floor and Yard Photo 6
Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



December 16, 2009 – Video of Second Floor Construction

The second floor is going in! Here is a new time-elapsed video showing the construction.

Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



November 20, 2009 – Mantrap Construction Video

Up to now much of the construction activity has been focused on our meet-me room. As you can see in our latest time-elapsed video, work has begun on our entry hallway, which features a mantrap security point visitors will pass through when accessing our datacenter.

Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



November 2, 2009 – Mantrap Construction

The construction of our mantrap is underway. When completed, it will feature a multi-factor, five-point authentication system through a combination of keycard use, PIN entry, and an iris scan. All visitors will be required to pass through the mantrap to enter our datacenter and/or view our meet-me room.

Man Trap Photo 1   Man Trap Photo 2   Man Trap Photo 3
Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



October 21, 2009 – Video of Meet-me Room Construction

Our meet-me room is approaching completion! Take a look at this time-elapsed video showing the installation of ladder racks. Carrier fiber from our cross-connect room runs inside conduit along the racks to the provider partner equipment inside our meet-me room.

Share and Enjoy:
  • Digg
  • Sphinn
  • del.icio.us
  • Facebook
  • Mixx
  • Google



August 31, 2009- WHIR tv Interviews Jordan Jacobs

While attending HostingCon, Phoenix NAP’s Director of Operations Jordan Jacobs was interviewed by WHIR tv about the facility build and the overall approach we are taking in the datacenter construction.